Mock Trail #2 Development

 

PROJECT STATUS

DESIGN


_______________________________
 PROJECT TIMELINE
FALL 2019- Applied for grant with Oregon Parks and Recreation.

SPRING 2020- OPRD Awarded grant to City.

FALL 2020-OPRD requested Archeological Survey report. Survey report submitted

FEBRUARY 2022-  Signed agreement with the ORPD, received notice to proceed.

SEPTEMBER 2022-Contracted

J-U-B Engineers for Design and Construction.

WINTER 2022- Anticipated bidding documents complete and open for bidding.
SPRING 2023- Construction contractor awarded bid.
SPRING 2023 To WINTER 2023- Construction.
JANUARY 2024- Construction complete.
FEBRUARY 2024- Trail #2 ribbon cutting ceremony.

Last Updated: 10/04/22

-Parks and Recreation-

Contact: Esmeralda Perches

DESCRIPTION

The city applied for a Regional Trail Plan Grant from Oregon Parks and Recreation Department for the development of Trail #2 listed on our Master Trail Plan. The plan is to remove the current asphalt and create a wide 10' ADA Accessible trail leading from Powerline Road to the pedestrian footbridge.

Why it's needed- This trail is needed to provide a critical link especially for persons with mobility constraints and who do not own an automobile and where there is no transit. It connects residents from the south hill region to the downtown region where they may access transportation, schools, retails, restaurants and supermarket.

FINANCIAL

Budget
Project Budget: $204,684.00
Expenditure to Date: $6,000.00
Total Cost: TBD                            

 