Business Center

 

PROJECT STATUS

IN PROGRESS


_______________________________
PROJECT TIMELINE
SUMMER 2018- City purchased old Post Office.
SPRING 2019- City contracted with Seder Architecture + Urban Design for the design of the Business Center.
SPRING 2022- City applied for Economic Development Administration Grant.
SUMMER 2022-Construction documents complete.

►WINTER 2022-PRESENT

EDA awarded City grant funds. EDA documentation review underway.

SPRING 2024- Construction bidding process will open.
TBD- Construction of Business Center.
TBD- Business Center Grand Opening.

Last Updated: 01/15/2024

 

 

 

 

 

 

 

 

-Community Development-

Project Contact: Brandon Seitz       Financial Contact: Melissa Ince

DESCRIPTION

The Umatilla Business Center and associated improvements will take up the greater park of a city block, with the exception of a warehouse on the southwest corner that will not be impacted by this project. The full Business Center including building, site and street improvements form a major component of the Umatilla Civic Center Master Plan. The project will include re-purposing an old Post Office, purchased by the city, and the construction of an addition to the Post Office. A two-story addition will be built immediately north of and adjoining the old Post Office forming an 11,500 sf mixed use facility fronting 6th Street. The city anticipates a total construction cost of $7.8 million dollars. Staff has applied for funds to assist with this project from Economic Development Administration, State of Oregon and Umatilla County. City has also reserved ARPA funds for this project.

Why it's needed-The goal of the Business Center is to energize the downtown and create a true city center composed of civic facilities, office & supporting functions, street & urban open space improvements and cultural event offering. The Business Center will offer incubator space designed to be leased for 1-3 years by emerging small businesses at below-market value.  

FINANCIAL

BUDGET
Project Budget: $8,397,580.00
Expenditure to Date: $489,484.00      
Total Cost: TBD                 
FUNDING SOURCES
Economic Development Administration $1,441,004.00                                           
State Legislature $1,800,000.00
Umatilla County $1,000,000.00
ARPA Funds $1,964,436.00
City Reserves $1,794,560.00

 

ENGAGEMENT

To stay informed subscribe here.

IMAGES

See below.

Click any thumbnail image to view a slideshow

Business Center Renderings
Business Center with Festival Renderings
Business Center Exterior Views
Umatilla Civic Center Renderings