Trail #2 Development

 

PROJECT STATUS

CONSTRUCTION DELAYS


_______________________________
PROJECT TIMELINE
FALL 2019- Applied for the grant with Oregon Parks and Recreation.

SPRING 2020- OPRD Awarded grant to City.

FALL 2020- OPRD requested Archeological Survey report.
FALL 2020- Archeological report submitted.
FEBRUARY 2022-  Signed agreement with the ORPD, received notice to proceed.

FALL 2022- PRESENT -Design and construction documents underway.

SUMMER 2023- Bidding OPEN.
SUMMER 2023- Award.
SPRING 2024-  Start Construction.
FALL 2024- Completion.
FALL 2024- Trail #2 ribbon cutting ceremony.
 

Last Updated: 01/15/2024

-Parks and Recreation-

Contact: Chris Waite

DESCRIPTION

The city applied for a Regional Trail Plan Grant from Oregon Parks and Recreation Department for the development of Trail #2 listed on our Master Trail Plan. The plan is to remove the current asphalt and create a wide 10' ADA Accessible trail leading from Powerline Road to the pedestrian footbridge.

Why it's needed- This trail is needed to provide a critical link especially for persons with mobility constraints and who do not own an automobile and where there is no transit. It connects residents from the south hill region to the downtown region where they may access transportation, schools, retails, restaurants and supermarket.

FINANCIAL

Budget
Project Budget: $204,684.00
Expenditure to Date: $6,000.00
Total Cost: TBD                            

 

ENGAGEMENT

None.

IMAGES

See below.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Click any thumbnail image to view a slideshow

Trail #2 Design
Trail #2 View
Trail #2 alt view